Legislators have put contractors of mega road projects in Kilifi County on the spot over the pace and quality of work.
Transport, Public Works and Housing Committee said work on the 48-kilometre Sabaki Bridge- Marikebuni-Marafa-Sosoni road was behind schedule by almost six months.
Committee vice chair Gathoni wa Muchomba said the contractor had done only 27 per cent of the project. The committee was inspecting roads in Kilifi…